Aramis takes next step towards investment decision

Carbon capture and storage

The Aramis project, a transport infrastructure for large-scale CO2 reduction, is making progress towards a final investment decision. The project is essential for achieving the climate goals and preserving the industry. The cabinet has also recognized this in the supplementary climate package. The initiators Gasunie, Energie Beheer Nederland (EBN), Shell, and TotalEnergies are working on completing the technical design phase and have recently decided to amend their cooperation as set out below.

From April 2025, Gasunie and EBN will take more control over the further development of the Aramis pipeline. TotalEnergies and Shell will remain involved as partners until the final investment decision, contributing essential technical knowledge and expertise to help realise the project.

The initiators aim for Gasunie and EBN to make an investment decision as soon as possible in 2026. After this, Shell and TotalEnergies will primarily focus on developing CO2 storage facilities.

In the supplementary climate package, the government has decided to allocate funds for EBN and Gasunie as prospective investors in the Aramis transport infrastructure. This support is intended to realise the project as quickly as possible, given its importance for achieving climate goals and maintaining industry in the Netherlands.

The Aramis CCS chain (Carbon Capture and Storage) will make a significant contribution to reducing CO2 emissions in the atmosphere by providing industries that are harder to make sustainable with the opportunity to transport and safely store captured CO2 in depleted gas fields under the North Sea. The Aramis project provides an open-access CO2 pipeline with a capacity of 22 million tonnes of CO2 per year and aims to be operational by the end of this decade.

 

More posts
Publication date: 10 June 2026
Carbon capture and storage

Working together on cross-border CO₂ infrastructure between the Netherlands and Germany

Publication date: 29 May 2026
Carbon capture and storage

Progress through Persistence: this was the seventh Carbon Storage Dialogues

Map CCS project Porthos
Publication date: 23 June 2025
Carbon capture and storage

EBN chooses Gradyent for unique CCS software model for Porthos

Joost Hooghiem, new director of CCS at EBN
Publication date: 15 May 2025
About EBN Carbon capture and storage

Joost Hooghiem new director of CCS

Publication date: 11 April 2025
Carbon capture and storage

The challenging path towards realising industrial carbon management

Text: Raad van State.
Publication date: 16 August 2023
Carbon capture and storage

Dutch Council of State gives Porthos the green light